Saudi Arabia's new procurement law: what changes for suppliers
Saudi Arabia's new Government Tenders and Procurement Law, issued by Royal Decree M/76 and published in Umm Al-Qura on 4 September 2026, takes effect 120 days after that publication (art. 101) and replaces the 2019 law, Royal Decree M/128 (art. 100). For a supplier the most visible change is direct purchase: the new law allows it up to an estimated cost of SAR 1,000,000 (art. 32), where the Ministry of Finance's table of amendments gives the old ceiling as SAR 100,000. Tenders put out under the 2019 law stay under it (Royal Decree M/76, item 3).
The official texts are in Arabic. Each passage on this page is the Arabic as Umm Al-Qura or the Ministry of Finance prints it, read on 11 October 2026, with TRINTA's translation under it.
M/76the royal decree that issues the law
4 September 2026published in Umm Al-Qura, the official gazette
120days from publication until it takes effect (art. 101)
SAR 1,000,000the new direct purchase ceiling (art. 32)
The law, the decree and the dates
The Council of Ministers approved the law by Decision 199 of 21/02/1448 AH, and Royal Decree M/76 of 27/02/1448 AH issued it; the first item of both approves the Government Tenders and Procurement Law in the form attached to it. The Ministry of Finance published the minister's statement on the Council's approval on 22/02/1448 AH.
Umm Al-Qura, the official gazette, published the law on 4 September 2026, a day it also dates 22/03/1448 AH. Article 101 starts the clock there: the law takes effect once 120 days have passed from that publication. Article 100 makes it replace the law issued by Royal Decree M/128 of 13/11/1440 AH, the 2019 law, and repeal whatever conflicts with it.
The new law runs to 101 articles and leaves many details to its Implementing Regulation. Article 99 gives the Ministry of Finance, working with the Local Content and Government Procurement Authority, 120 days from publication to prepare it, and the Regulation applies from the day the law does. Article 98 has the Council of Ministers issue, in the same 120 days, the regulations it lists, the Preference Regulation among them.
Decision 199 also names the bodies the law calls competent for unified procurement: the General Authority for Military Industries for military and security procurement, and the Expenditure Efficiency and Government Projects Authority for all other government procurement (item 10). Items on the lists they keep are bought only through the framework agreements they conclude (art. 15).
يحل النظام محل نظام المنافسات والمشتريات الحكومية، الصادر بالمرسوم الملكي رقم (م/128) وتاريخ 1440/11/13هـ، ويُلغي ما يتعارض معه من أحكام.
TranslationThe Law replaces the Government Tenders and Procurement Law issued by Royal Decree No. (M/128) dated 13/11/1440 AH, and repeals any provisions that conflict with it.
تتولى الوزارة -بالتنسيق مع الهيئة- إعداد اللائحة خلال (مائة وعشرين) يومًا من تاريخ نشر النظام في الجريدة الرسمية، وتصدر بقرار من الوزير، ويعمل بها من تاريخ العمل بالنظام.
TranslationThe Ministry (in coordination with the Authority) prepares the Regulation within (one hundred and twenty) days of the date the Law is published in the Official Gazette; it is issued by decision of the Minister and applies from the date the Law takes effect.
ويصدر مجلس الوزراء اللوائح المشار إليها في هذه المادة خلال (مائة وعشرين) يومًا من تاريخ نشر النظام في الجريدة الرسمية، ويعمل بها من تاريخ العمل بالنظام.
TranslationThe Council of Ministers issues the regulations referred to in this article within (one hundred and twenty) days of the date the Law is published in the Official Gazette, and they apply from the date the Law takes effect.
عاشرًا: تكون الجهة المختصة بالشراء الموحد الواردة في النظام المشار إليه في البند (أولًا) من هذا القرار هي:
1- الهيئة العامة للصناعات العسكرية، فيما يتعلق بالمشتريات العسكرية والأمنية.
2- هيئة كفاءة الإنفاق والمشروعات الحكومية، فيما يتعلق بالمشتريات الحكومية عدا المشتريات العسكرية والأمنية.
TranslationTenth: the body competent for unified procurement under the Law referred to in item (First) of this decision is: 1. The General Authority for Military Industries, for military and security procurement. 2. The Expenditure Efficiency and Government Projects Authority, for government procurement other than military and security procurement.
لا يجوز للجهة الحكومية تأمين المشتريات أو تنفيذ الأعمال الواردة في القوائم التي تعدها الجهة المختصة بالشراء الموحد إلا من خلال الاتفاقيات الإطارية التي أبرمتها الجهة المختصة بالشراء الموحد.
TranslationA government entity may not procure items or carry out works on the lists the unified-procurement body prepares except through the framework agreements that body has concluded.
Tenders already put out
The decree keeps the 2019 law for what was put out under it: government works and procurement put out while that law was in force stay under it. The Minister of Finance may apply some provisions of the new law to them, under a mechanism he sets, without prejudice to the measures already taken on them (item 3).
Exceptions granted to government entities under article 95 of the 2019 law continue, as do exceptions limited in time or tied to one project until it is completed, and those granted to the Public Investment Fund and the Saudi Central Bank (item 4).
Matters and requests still pending before the committees of articles 86 and 88 of the 2019 law go to the committees the new law forms under articles 84 and 87 (Decision 199, item 7).
ثالثًا: مع مراعاة ما ورد في البند (ثانيًا) من هذا المرسوم، ودون إخلال بما ورد في البند (خامسًا) من المرسوم الملكي رقم (م/128) بتاريخ 1440/11/13هـ، يطبق نظام المنافسات والمشتريات الحكومية، الصادر بالمرسوم الملكي رقم (م/128) بتاريخ 1440/11/13هـ على الأعمال والمشتريات الحكومية التي طرحت أثناء سريان ذلك النظام. واستثناءً من ذلك، يجوز لوزير المالية تطبيق بعض أحكام النظام -المشار إليه في البند (أولًا) من هذا المرسوم- على الأعمال والمشتريات التي طرحت أثناء سريان النظام، الصادر بالمرسوم الملكي رقم (م/128) بتاريخ 1440/11/13هـ، وفق آلية يضعها، وذلك دون إخلال بالإجراءات التي اتخذت في شأن تلك الأعمال والمشتريات قبل نفاذ النظام المشار إليه في البند (أولًا) من هذا المرسوم.
TranslationThird: with due regard to item (Second) of this decree, and without prejudice to item (Fifth) of Royal Decree No. (M/128) dated 13/11/1440 AH, the Government Tenders and Procurement Law issued by Royal Decree No. (M/128) dated 13/11/1440 AH applies to the government works and procurement put out while that law was in force. By way of exception, the Minister of Finance may apply some provisions of the Law (referred to in item (First) of this decree) to works and procurement put out while the law issued by Royal Decree No. (M/128) dated 13/11/1440 AH was in force, under a mechanism he sets, without prejudice to the measures taken on those works and procurement before the Law referred to in item (First) of this decree takes effect.
رابعًا: استمرار الاستثناءات الصادرة للجهات الحكومية من نظام المنافسات والمشتريات الحكومية -الصادر بالمرسوم الملكي رقم (م/128) بتاريخ 1440/11/13هـ- وفق المادة (الخامسة والتسعين) منه، وكذلك الاستثناءات المحددة بمدة أو المرتبطة بمشروع معين إلى حين الانتهاء منه، وكذلك الاستثناءات الصادرة لكلٍّ من: (صندوق الاستثمارات العامة، والبنك المركزي السعودي).
TranslationFourth: the exceptions granted to government entities from the Government Tenders and Procurement Law (issued by Royal Decree No. (M/128) dated 13/11/1440 AH) under its article ninety-five continue, as do exceptions limited in time or tied to a specific project until it is completed, and the exceptions granted to each of the Public Investment Fund and the Saudi Central Bank.
سابعًا: تحال الأعمال والطلبات القائمة التي لم يُفصل فيها بشكل نهائي لدى اللجان المشكلة بموجب المادتين (السادسة والثمانين) و(الثامنة والثمانين) من نظام المنافسات والمشتريات الحكومية، الصادر بالمرسوم الملكي رقم (م/128) وتاريخ 1440/11/13هـ، إلى اللجان التي ستشكل بموجب المادتين (الرابعة والثمانين) و(السابعة والثمانين) من النظام المشار إليه في البند (أولًا) من هذا القرار، وفقًا للاختصاص.
TranslationSeventh: matters and requests pending without a final decision before the committees formed under articles eighty-six and eighty-eight of the Government Tenders and Procurement Law issued by Royal Decree No. (M/128) dated 13/11/1440 AH are referred to the committees to be formed under articles eighty-four and eighty-seven of the Law referred to in item (First) of this decision, according to their competence.
What changes for a supplier
Each change below is stated in the new law's own words, with the article. Where the Ministry of Finance's table of the main amendments states the old rule, it is given as the Ministry gives it, and the table's line is quoted under the article.
Direct purchase up to SAR 1,000,000
A government entity may buy directly when the estimated cost of the works and procurement does not exceed SAR 1,000,000, and in that case local small and medium enterprises have priority (art. 32, para. 3). The entity must state and document why it used direct purchase (art. 32). The Ministry of Finance gives the old ceiling as SAR 100,000.
للجهة الحكومية التعاقد بأسلوب الشراء المباشر -مع توضيح أسباب استخدام هذا الأسلوب وتوثيقه، وبما لا يخل بمبادئ المنافسة وكفاءة الإنفاق- في الحالات الآتية:
TranslationA government entity may contract by direct purchase (stating the reasons for using this method and documenting them, without prejudice to the principles of competition and spending efficiency) in the following cases:
3- إذا كانت التكلفة التقديرية للأعمال والمشتريات لا تتجاوز (مليون) ريال. وفي هذه الحالة تكون الأولوية للمنشآت الصغيرة والمتوسطة المحلية.
Translation3. If the estimated cost of the works and procurement does not exceed (one million) riyals. In this case, priority goes to local small and medium enterprises.
رفع الحد الأعلى للتكلفة التقديرية لإتاحة استخدام أسلوب الشراء المباشر من (100 ألف) إلى (مليون) ريال.
TranslationRaising the upper limit of the estimated cost for using direct purchase from (100 thousand) to (one million) riyals.
Six more grounds for direct purchase
Article 32 now also allows direct purchase for research, development or innovation, for work only one liberal professional offers, for software licences and website subscriptions, for specialised scientific journals, for space at exhibitions, events and conferences, and for training government staff (paras. 6 to 11). The Ministry of Finance lists each of the six as newly allowed.
6- إذا كانت الأعمال والمشتريات لغرض البحث أو التطوير أو الابتكار وفقاً لما تحدده اللائحة.
7- إذا كانت الأعمال والمشتريات متوافرة حصريًّا لدى ممارس واحد من ممارسي المهن الحرة. ولا يخلّ بذلك أن تكون الأعمال والمشتريات متوافرة لدى غير ممارسي المهن الحرة.
8- إذا كان التعاقد لتأمين مشتريات الرخص والبرامج الإلكترونية أو الاشتراك في المواقع الإلكترونية.
9- إذا كان التعاقد لتأمين مشتريات المجلات العلمية المتخصصة أو الاشتراك فيها.
10- إذا كان التعاقد لحجز واستئجار المساحات في المعارض والفعاليات والمؤتمرات.
11- إذا كان التعاقد لتدريب موظفي الجهات الحكومية.
Translation6. If the works and procurement are for research, development or innovation, as the Regulation sets. 7. If the works and procurement are available exclusively from a single liberal professional; their being available from others who are not liberal professionals does not affect this. 8. If the contract is to procure licences and software, or subscriptions to websites. 9. If the contract is to procure specialised scientific journals, or subscriptions to them. 10. If the contract is to book and rent space at exhibitions, events and conferences. 11. If the contract is to train the staff of government entities.
إتاحة استخدام أسلوب الشراء المباشر لأغراض البحث أو التطوير أو الابتكار.
إتاحة استخدام أسلوب الشراء المباشر في حال توافر الأعمال والمشتريات لدى أحد ممارسي المهن الحرة.
إتاحة استخدام أسلوب الشراء المباشر لمشتريات الرخص والبرامج الإلكترونية أو الاشتراك في المواقع الإلكترونية.
إتاحة استخدام أسلوب الشراء المباشر لمشتريات المجلات العلمية المتخصصة أو الاشتراك فيها.
إتاحة استخدام أسلوب الشراء المباشر لحجز واستئجار المساحات في المعارض والفعاليات والمؤتمرات.
إتاحة استخدام أسلوب الشراء المباشر لتدريب موظفي الجهات الحكومية.
TranslationAllowing direct purchase for research, development or innovation. Allowing direct purchase where the works and procurement are available from one liberal professional. Allowing direct purchase for licences and software, or subscriptions to websites. Allowing direct purchase for specialised scientific journals, or subscriptions to them. Allowing direct purchase to book and rent space at exhibitions, events and conferences. Allowing direct purchase to train the staff of government entities.
Limited competition needs its reasons
An entity using limited competition must state why, and why public competition does not suit (art. 30); liberal professionals are a case of their own (art. 30, para. 4). The Ministry of Finance says the old ground of an estimated value up to SAR 500,000 is gone.
للجهة الحكومية التعاقد بأسلوب المنافسة المحدودة -مع توضيح أسباب اللجوء إلى هذا الأسلوب وبيان عدم ملاءمة المنافسة العامة- في الحالات الآتية:
TranslationA government entity may contract by limited competition (stating the reasons for using this method and why public competition is not suitable) in the following cases:
اشتراط على الجهة الحكومية أن توضّح أسباب اللجوء إلى هذا الأسلوب وبيان عدم ملاءمة المنافسة العامة
TranslationRequiring the government entity to state the reasons for using this method and why public competition is not suitable.
Bids stay valid 90 working days
Bids are valid for 90 working days from the date set for opening them, and a bidder that withdraws in that time loses its initial guarantee (art. 39, para. 1). The Ministry of Finance gives the old period as 90 calendar days.
تكون مدة سريان العروض في المنافسات (تسعين) يوم عمل من التاريخ المحدد لفتح العروض، فإن سحب المتنافس عرضه خلال هذه المدة؛ فلا يعاد إليه ضمانه الابتدائي.
TranslationBids in tenders remain valid for (ninety) working days from the date set for opening them; if a bidder withdraws its bid within this period, its initial guarantee is not returned.
تعديل مدة سريان العروض في المنافسات من (90) يوم تقويمي إلى (90) يوم عمل.
TranslationChanging the validity of bids in tenders from (90) calendar days to (90) working days.
A standstill of 3 to 10 working days
After the award decision is notified, the entity waits at least 3 and at most 10 working days before completing the contract, so that bidders can file a grievance (art. 50, para. 1). The Ministry of Finance gives the old minimum as 5 working days.
تلتزم الجهة الحكومية -بعد صدور قرار الترسية وإشعار المتنافسين به- بفترة توقف لا تقل عن (ثلاثة) أيام عمل ولا تزيد على (عشرة) أيام عمل؛ لا يجوز خلالها استكمال إجراءات التعاقد وتوقيع العقد؛ وذلك لتمكين المتنافسين من التظلم من قرار الترسية.
TranslationAfter the award decision is issued and the bidders are notified of it, the government entity observes a standstill period of no less than (three) and no more than (ten) working days, during which the contracting procedures may not be completed nor the contract signed, so that bidders can file a grievance against the award decision.
تقليص الحد الأدنى لفترة التوقف من (5) أيام عمل إلى (3) أيام عمل.
TranslationReducing the minimum standstill period from (5) working days to (3) working days.
No final guarantee up to SAR 300,000
The winner lodges a final guarantee of 5% of the contract value within 15 working days of being notified (art. 59, para. 1), and none is required for works and procurement up to SAR 300,000 (art. 59, para. 2). The Ministry of Finance gives the old exemption as SAR 100,000, and says the exemption for companies at least 51% state-owned is gone.
على صاحب العرض الفائز بعد إبلاغه بقرار الترسية تقديمُ ضمان نهائي بنسبة (5٪) من قيمة العقد، وذلك خلال (خمسة عشر) يوم عمل من تاريخ إبلاغه بالقرار.
TranslationAfter being notified of the award decision, the winning bidder must provide a final guarantee of (5%) of the contract value within (fifteen) working days of being notified.
أ- إذا كانت قيمة الأعمال والمشتريات لا تتجاوز (ثلاثمائة) ألف ريال.
Translation(a) If the value of the works and procurement does not exceed (three hundred) thousand riyals. [The first case in which no final guarantee is required.]
إلغاء استثناء تقديم الضمان النهائي حين التعاقد مع الشركات التي تملك الدولة فيها نسبة لا تقل عن (51 %) من رأس مالها
TranslationEnding the exemption from the final guarantee when contracting with companies in which the state owns no less than (51%) of the capital.
Change orders, with caps
The entity may add new items up to 10% of the value of the contract or purchase order with the contractor's consent, increase existing items up to 20% (with the contractor's consent for the increase beyond 10%), and reduce existing items up to 20%, or further with consent (art. 67, para. 1). New and increased items together may not exceed 20% (art. 67, para. 2), and non-financial terms change by agreement (art. 67, para. 3). The Ministry of Finance lists these among the amendments.
أ- إصدار أوامر تغيير بإضافة بنود جديدة إلى العقد أو إلى أمر الشراء الصادر بناء على اتفاقية إطارية؛ بما لا يتجاوز (10٪) من قيمة العقد أو أمر الشراء، وذلك بعد أخذ موافقة المتعاقد معه على ذلك.
ب- إصدار أوامر تغيير بزيادة البنود القائمة للعقد أو لأمر الشراء الصادر بناء على اتفاقية إطارية؛ بما لا يتجاوز (20٪) من قيمة العقد أو أمر الشراء، على أن تؤخذ موافقة المتعاقد معه على الزيادة التي تتجاوز (10٪) من هذه الزيادة.
ج- إصدار أوامر تغيير بتخفيض البنود القائمة للعقد أو لأمر الشراء الصادر بناء على اتفاقية إطارية؛ بما لا يتجاوز (20٪) من قيمة العقد أو أمر الشراء. ويجوز تجاوز هذه النسبة على أن تؤخذ موافقة المتعاقد معه.
Translation(a) Issue change orders adding new items to the contract, or to a purchase order issued under a framework agreement, up to (10%) of the value of the contract or purchase order, after obtaining the contractor's consent. (b) Issue change orders increasing the existing items of the contract, or of a purchase order issued under a framework agreement, up to (20%) of the value of the contract or purchase order, the contractor's consent being obtained for the increase that exceeds (10%) of this increase. (c) Issue change orders reducing the existing items of the contract, or of a purchase order issued under a framework agreement, up to (20%) of the value of the contract or purchase order; this percentage may be exceeded with the contractor's consent.
يتعين عند إصدار أوامر تغيير بإضافة بنود جديدة إلى العقد أو إلى أمر الشراء الصادر بناء على اتفاقية إطارية وزيادة بنوده القائمة معًا وفقًا لحكم الفقرتين الفرعيتين (أ) و(ب) من الفقرة (1) من هذه المادة؛ ألا تتجاوز قيمة الزيادة الكلية (20٪) من قيمة العقد أو أمر الشراء.
TranslationWhen change orders both add new items to the contract (or to a purchase order issued under a framework agreement) and increase its existing items, under subparagraphs (a) and (b) of paragraph (1) of this article, the total increase may not exceed (20%) of the value of the contract or purchase order.
للجهة الحكومية تغيير الأحكام غير المالية في العقد بالاتفاق مع المتعاقد معه، وذلك دون إخلال بأحكام النظام واللائحة ولائحة التفضيل والأحكام الإلزامية الواردة في نماذج العقود المشار إليها في الفقرة (2) من المادة (الثالثة عشرة) من النظام.
TranslationThe government entity may change the non-financial terms of the contract by agreement with the contractor, without prejudice to the provisions of the Law, the Regulation, the Preference Regulation and the mandatory provisions of the contract models referred to in paragraph (2) of article thirteen of the Law.
إتاحة إصدار أوامر تغيير بإضافة بنود جديدة إلى العقد أو إلى أمر الشراء لاتفاقية إطارية بما لا يتجاوز (10%) بعد أخذ موافقة المتعاقد معه.
TranslationAllowing change orders adding new items to the contract, or to a purchase order under a framework agreement, up to (10%) after obtaining the contractor's consent.
إلزام الجهات الحكومية عند إصدار أوامر تغيير بإضافة بنود جديدة أو زيادة بنود قائمة ألا تتجاوز قيمة الزيادة الكلية (20%) من قيمة العقد أو أمر الشراء.
TranslationRequiring government entities, when issuing change orders that add new items or increase existing ones, to keep the total increase within (20%) of the value of the contract or purchase order.
Lower caps on penalties
A delay penalty may not exceed 6% of a supply contract's value or 15% of other contracts, unless the Minister approves more and bidders were told before they bid (art. 70); the penalty for falling short in continuous-service contracts may not exceed 15% (art. 71). The Ministry of Finance gives the old cap as 20% for both.
إذا تأخر المتعاقد معه في تنفيذ العقد عن الموعد المحدد، فتفرض عليه غرامة تأخير لا تتجاوز (6٪) من قيمة عقد التوريد، ولا تتجاوز (15٪) من قيمة العقود الأخرى، وتجوز -في الحالات التي تستلزم ذلك- زيادة تلك النسب بموافقة مسبقة من الوزير، على أن تكون تلك الزيادة قد وضحت للمتنافسين قبل تقديم عروضهم.
TranslationIf the contractor is late in performing the contract beyond the set date, a delay penalty is imposed of no more than (6%) of the value of a supply contract and no more than (15%) of the value of other contracts; where needed, those rates may be raised with the Minister's prior approval, provided the increase was made clear to bidders before they submitted their bids.
إذا قصّر المتعاقد معه في عقود الخدمات ذات التنفيذ المستمر في تنفيذ التزاماته لأسباب غير خارجة عن إرادته؛ فتُفرض عليه غرامة لا تتجاوز (15٪) من قيمة العقد، مع حسم قيمة الأعمال التي لم تُنفذ في كل الأحوال.
TranslationIf, in continuous-service contracts, the contractor falls short in performing its obligations for reasons that are not beyond its control, a penalty of no more than (15%) of the contract value is imposed, and the value of the work not performed is deducted in all cases.
تعديل الحد الأقصى لغرامة التقصير في العقود ذات التنفيذ المستمر، من (20%) إلى (15%) من قيمة العقد.
TranslationChanging the maximum shortfall penalty in continuous-performance contracts from (20%) to (15%) of the contract value.
No new award while dues go unpaid
A government entity that owes its contractors for works and procurement, and has not acted on it despite a notice from the Ministry of Finance, may not issue a new award decision (art. 91, para. 2). The Ministry of Finance lists it as a new article.
لا يجوز للجهة الحكومية -في الحالة التي يكون عليها مستحقات للمتعاقدين معها لتنفيذ أعمال وتأمين مشتريات ولم تتخذ في شأنها الإجراءات اللازمة على الرغم من إشعار الوزارة لها- إصدار قرار ترسية جديد؛ وفقًا لما توضحه اللائحة في هذا الشأن.
TranslationA government entity (where it owes amounts to its contractors for works carried out and procurement supplied and has not taken the necessary measures on them despite notice from the Ministry) may not issue a new award decision, as the Regulation sets out in this respect.
إضافة مادة جديدة تنص على أنه لا يجوز للجهة الحكومية -في الحالة التي يكون عليها مستحقات للمتعاقدين معها لتنفيذ أعمال وتأمين مشتريات ولم تتخذ في شأنها الإجراءات اللازمة على الرغم من إشعار الوزارة لها- إصدار قرار ترسية جديد؛ وفقاً لما توضحه اللائحة في هذا الشأن.
TranslationAdding a new article providing that a government entity (where it owes amounts to its contractors for works and procurement and has not taken the necessary measures on them despite notice from the Ministry) may not issue a new award decision, as the Regulation sets out in this respect.
Grievances carry a deposit
A grievance comes with 0.5% of the bid's value, or SAR 15,000 against a prequalification decision, returned if the grievance is upheld (art. 84, para. 4). It is filed with the entity within 5 working days against a decision taken before the award, and within the standstill period against the award (art. 85, para. 1).
يقدم المتظلم مبلغًا بنسبة (0,5٪) من قيمة عرضه؛ وفي حالة التظلم على قرار التأهيل المسبق يقدّم مبلغ (خمسة عشر) ألف ريال، وتعاد إليه المبالغ التي قدمها إذا ثبتت صحة التظلم.
TranslationThe person filing a grievance pays an amount of (0.5%) of the value of its bid; for a grievance against a prequalification decision it pays (fifteen) thousand riyals; the amounts paid are returned if the grievance is upheld.
لكل متنافس الحق في التظلم أمام الجهة الحكومية من أي قرار اتخذته قبل قرار الترسية، وذلك خلال (خمسة) أيام عمل من تاريخ صدور القرار، وله كذلك التظلم أمام الجهة الحكومية من قرار الترسية، وذلك خلال فترة التوقف المشار إليها في المادة (الخمسين) من النظام.
TranslationEvery bidder has the right to file a grievance with the government entity against any decision it takes before the award decision, within (five) working days of the decision, and also against the award decision, within the standstill period referred to in article fifty of the Law.
إلزام المتظلم بتقديم مبلغ بنسبة (0.5%) من قيمة عرضه أو (15 ألف) ريال في حالة التظلم على قرار التأهيل المسبق.
TranslationRequiring the person filing a grievance to pay (0.5%) of the value of its bid, or (15 thousand) riyals for a grievance against a prequalification decision.
One committee opens and examines the bids
A single committee opens and examines the bids and recommends the award (art. 43, para. 1); the Ministry of Finance says the opening and examination committees were merged into one. The unified-procurement body and the Local Content and Government Procurement Authority may each send a representative to the examination, with a member's powers (art. 43, para. 5).
تكوّن لجنة -أو أكثر- بقرار من رئيس الجهة الحكومية -أو من يفوضه- لفتح العروض وفحصها، وفقًا لما توضحه اللائحة. وتتولى هذه اللجنة فتح العروض وفحصها وتقديم توصياتها بالترسية على أفضل العروض في محضر يُعد لذلك، وفقًا لأحكام النظام.
TranslationOne or more committees are formed by decision of the head of the government entity (or a delegate) to open and examine bids, as the Regulation sets out. This committee opens and examines the bids and recommends the award to the best bids in minutes prepared for that purpose, under the provisions of the Law.
للجهة المختصة بالشراء الموحد وللهيئة ندب ممثل لكل منهما للمشاركة في مناقشات فحص العروض، ويكون لهما ما لأعضاء اللجنة من صلاحيات.
TranslationThe unified-procurement body and the Authority may each delegate a representative to take part in the discussions examining the bids, with the powers of the committee's members.
إتاحة مشاركة ممثل من هيئة المحتوى المحلي والمشتريات الحكومية في مناقشات فحص العروض ويكون له ما لأعضاء لجنة فتح العروض وفحصها من صلاحيات.
TranslationAllowing a representative of the Local Content and Government Procurement Authority to take part in the bid examination discussions, with the powers of the members of the bid opening and examination committee.
No country of origin in specifications
Specifications may not name a trademark or trade name, fit only certain suppliers, or refer to a country of origin, without prejudice to the preference for local content (art. 22, para. 1); the Regulation sets the cases where a brand or an origin may be named (art. 22, para. 2). The Ministry of Finance lists the country-of-origin rule among the amendments.
يجب أن تكون الشروط والمواصفات الفنية للأعمال والمشتريات المطروحة تفصيلية دقيقة واضحة، وأن تُراعى فيها المواصفات القياسية الوطنية المعتمدة أو المواصفات العالمية فيما ليس له مواصفات وطنية معتمدة، وألا تتضمن تحديد علامة تجارية أو اسمًا تجاريًّا بعينه أو وضع مواصفات لا تنطبق إلا على موردين أو مقاولين أو متعهدين بعينهم أو الإشارة إلى بلد المنشأ، مع عدم الإخلال بأحكام تفضيل المحتوى المحلي.
TranslationThe technical conditions and specifications of the works and procurement put out must be detailed, precise and clear; they must observe the approved national standards, or international specifications where there is no approved national one; and they must not name a specific trademark or trade name, set specifications that only certain suppliers, contractors or undertakers can meet, or refer to the country of origin, without prejudice to the provisions on preference for local content.
استثناء من حكم الفقرة (1) من هذه المادة، تجوز الإشارة إلى علامة تجارية أو اسم تجاري بعينه أو إلى بلد المنشأ وفق الحالات والإجراءات التي تحددها اللائحة.
TranslationBy way of exception to paragraph (1) of this article, a specific trademark or trade name, or the country of origin, may be referred to in the cases and under the procedures the Regulation sets.
إلزام الجهات الحكومية بعدم الإشارة إلى بلد المنشأ، وإتاحة الاستثناء من ذلك وفق الحالات والإجراءات التي تحددها اللائحة
TranslationRequiring government entities not to refer to the country of origin, with exceptions in the cases and under the procedures the Regulation sets.
Questions answered before the deadline
Bidders may put questions on the tender documents, and the entity must answer them before the period for bids ends (art. 26): a chapter the Ministry of Finance says is new.
للمتنافسين -بعد حصولهم على وثائق المنافسة- التقدم إلى الجهة الحكومية بأي استفسار في شأن ما ورد في تلك الوثائق من بيانات، وعلى الجهة الحكومية الرد على ما يرد إليها من استفسارات قبل انتهاء مدة تلقي العروض؛ وفقًا لما توضحه اللائحة.
TranslationBidders, once they have obtained the tender documents, may put any question to the government entity about the information in those documents, and the government entity must answer the questions it receives before the period for receiving bids ends, as the Regulation sets out.
تم إضافة فصل جديد في النظام لتنظيم استفسارات المتنافسين بعد طرح المنافسة، والتأكيد على الجهة الحكومية الرد على ما يرد إليها من استفسارات قبل انتهاء مدة تلقي العروض
TranslationA new chapter was added to the Law to regulate bidders' questions after the tender is put out, confirming that the government entity must answer the questions it receives before the period for receiving bids ends.
Faster decisions inside the buyer
The head of an entity may delegate decisions up to SAR 50,000,000 (art. 51, para. 1), and the Ministry of Finance reviews the contracts the Regulation lists within 4 working days, after which its silence counts as approval (art. 57, para. 1). The Ministry gives the old figures as SAR 10,000,000 and 15 days.
فيما لم يرد في شأنه نص خاص في النظام، تكون صلاحية البتّ في جميع الإجراءات واتخاذ القرارات وفقًا لأحكام النظام واللائحة لرئيس الجهة الحكومية، وله تفويض من يراه من مسؤولي الجهة الحكومية بما لا يزيد على (خمسين) مليون ريال، على أن يراعى التدرج في التفويض بحسب مسؤولية الشخص المفوض.
TranslationExcept where the Law makes special provision, the power to decide on all procedures and take decisions under the Law and the Regulation lies with the head of the government entity, who may delegate it to officials of the entity of his choosing up to (fifty) million riyals, delegating in steps according to the responsibility of the delegate.
تلتزم الجهات الحكومية بعرض عقودها -التي تحددها اللائحة- على الوزارة لمراجعتها قبل توقيعها، وعلى الوزارة مراجعتها خلال (أربعة) أيام عمل من تاريخ ورودها إليها. فإن لم تردّ الوزارة خلال هذه المدة عُدّت موافقة. ويستثنى من حكم هذه المادة الجهات التي ليس لها اعتمادات بالميزانية العامة للدولة.
TranslationGovernment entities must submit their contracts (those the Regulation specifies) to the Ministry for review before signing them, and the Ministry must review them within (four) working days of receiving them. If the Ministry does not reply within that period, this counts as approval. Entities without appropriations in the state's general budget are excepted from this article.
رفع حد تفويض من يراه رئيس الجهة الحكومية للبت في الإجراءات واتخاذ القرارات من (10 مليون ريال) إلى (50 مليون ريال)
TranslationRaising the limit of the delegation the head of the government entity may give to decide on procedures and take decisions from (10 million riyals) to (50 million riyals).
تقليص الحد الأعلى لفترة إجازة العقود من قبل وزارة المالية من (15) يوم إلى (4) أيام عمل.
TranslationReducing the maximum period for the Ministry of Finance to clear contracts from (15) days to (4) working days.
What the text says to a foreign supplier
When a government entity deals with persons licensed outside the Kingdom for procurement or works inside it, article 3 has it make sure that no more than one person licensed inside the Kingdom is qualified for the job (para. 2); the Regulation sets the conditions and the special provisions (paras. 2 and 3). Works and procurement carried out outside the Kingdom follow special provisions the Regulation sets (art. 11).
A bid comes with an initial guarantee of 1% to 2% of its value (art. 41). Guarantees are accepted as a letter from a local bank, as a letter from a bank outside the Kingdom presented through a local bank, or in another form the Regulation sets (art. 61).
Contracts and their documents are drafted in Arabic; another language may sit beside it, but the Arabic governs interpretation, performance, specifications, drawings and correspondence (art. 52, para. 2). Entities funded from the state budget pay in Saudi riyals; another currency needs the Ministry of Finance's approval, or its silence for a period the Regulation sets, and is named in the tender documents (art. 62).
Contracts are made directly with those authorised to work, without intermediaries; a distributor or agent accredited by the original manufacturer, a franchise holder and those licensed to act as intermediaries are not intermediaries (art. 90).
على الجهة الحكومية عند تعاملها مع أشخاص مرخص لهم خارج المملكة لتأمين مشتريات أو تنفيذ أعمال داخل المملكة التأكد من عدم توافر أكثر من شخص مرخص له داخل المملكة مؤهل لتأمين المشتريات أو تنفيذ الأعمال المطلوبة. وتحدد اللائحة الشروط والضوابط اللازمة لتطبيق حكم هذه الفقرة.
TranslationWhen a government entity deals with persons licensed outside the Kingdom to supply procurement or carry out works inside the Kingdom, it must make sure that no more than one person licensed inside the Kingdom is available who is qualified to supply the procurement or carry out the works required. The Regulation sets the conditions and controls needed to apply this paragraph.
دون إخلال بما ورد في الفقرة (2) من هذه المادة، تحدد اللائحة الأحكام الخاصة لحالات التعامل مع أشخاص مرخص لهم خارج المملكة لتأمين مشتريات أو تنفيذ أعمال داخل المملكة، وتطبق الجهة الحكومية فيما عدا ذلك أحكام النظام على تلك الحالات.
TranslationWithout prejudice to paragraph (2) of this article, the Regulation sets the special provisions for dealing with persons licensed outside the Kingdom to supply procurement or carry out works inside the Kingdom; beyond that, the government entity applies the provisions of the Law to those cases.
تحدد اللائحة الأحكام الخاصة بالأعمال والمشتريات التي تنفّذ خارج المملكة، وتطبق الجهة الحكومية فيما عدا ذلك أحكام النظام على تلك الأعمال والمشتريات.
TranslationThe Regulation sets the special provisions for works and procurement carried out outside the Kingdom; beyond that, the government entity applies the provisions of the Law to those works and procurement.
يُقدم المتنافس مع عرضه ضمانًا ابتدائيًّا بنسبة تتراوح من (1٪) إلى (2٪) من قيمة العرض. ولا يُقبل العرض الذي لم يقدم معه ذلك الضمان.
TranslationThe bidder submits with its bid an initial guarantee of between (1%) and (2%) of the bid value. A bid submitted without that guarantee is not accepted.
تقبل الضمانات إذا كانت وفق أحد الأشكال الآتية:
1- خطاب ضمان بنكي من أحد البنوك المحلية.
2- خطاب ضمان بنكي من بنك خارج المملكة يقدم بوساطة أحد البنوك المحلية.
3- أي شكل آخر تحدده اللائحة.
TranslationGuarantees are accepted in one of the following forms: 1. A bank guarantee letter from a local bank. 2. A bank guarantee letter from a bank outside the Kingdom, presented through a local bank. 3. Any other form the Regulation sets.
تُصاغ العقود ووثائقها وملحقاتها باللغة العربية، ويجوز استخدام لغة أخرى إلى جانب العربية على أن تكون العربية هي المعتمَدة في تفسير العقد وتنفيذه وتحديد مواصفاته ومخططاته والمراسلات المتعلقة به.
TranslationContracts, their documents and annexes are drafted in Arabic. Another language may be used alongside Arabic, provided Arabic is the authoritative language for interpreting and performing the contract, setting its specifications and drawings, and for the correspondence about it.
على الجهة الحكومية -التي يخصص لها بنود ضمن الميزانية العامة للدولة- دفع قيمة العقود بالريال السعودي، ويجوز بعد موافقة الوزارة أو مضي المدة التي تحددها اللائحة دون اعتراض منها أن تُدفع بعملة أخرى على أن تحدد تلك العملة في وثائق المنافسة في المنافسات التي تتطلب ذلك.
TranslationA government entity with items in the state's general budget pays the value of contracts in Saudi riyals; with the Ministry's approval, or once the period the Regulation sets passes without its objection, payment may be made in another currency, which is specified in the tender documents of the tenders that require it.
يكون التعاقد مع المصرح لهم بالعمل مباشرة، ولا تجوز الوساطة في التعاقد، ولا يُعد وسيطًا الموزّع أو الوكيل المعتمد من المنتج الأصلي أو حامل الامتياز ومن في حكمهم أو المرخص لهم نظامًا للقيام بأعمال الوساطة.
TranslationContracts are concluded directly with those authorised to work, and intermediation in contracting is not allowed. A distributor or agent accredited by the original manufacturer, a franchise holder and those in a similar position, or those licensed by law to act as intermediaries, are not considered intermediaries.
Local content and preference
Priority goes to local small and medium enterprises, to local content and to companies listed on the financial market, by the mechanism of the Preference Regulation (art. 9). Entities coordinate with the Local Content and Government Procurement Authority on local content requirements when they plan their purchases (art. 12, para. 2), an obligation the Ministry of Finance lists as new.
The Preference Regulation must set how local content is preferred and calculated, including the preference percentage in the technical and financial evaluation of bids or the mandatory share of local content in the contract's value (art. 98, para. 2). The decree keeps the current regulations in force, the Preference Regulation of Council of Ministers Decision 245 among them (item 5), and Decision 199 asks the Ministry and the Authority to check them against the new law (item 5, para. 2).
The Authority may also contract for industrial localisation and knowledge transfer, under separate rules the Ministry issues with it (art. 34).
تكون الأولوية في التعامل للمنشآت الصغيرة والمتوسطة المحلية وللمحتوى المحلي وللشركات المدرجة في السوق المالية. وتوضح لائحة التفضيل آلية ذلك.
TranslationPriority in dealings goes to local small and medium enterprises, to local content and to companies listed on the financial market. The Preference Regulation sets out the mechanism.
على الجهة الحكومية عند التخطيط المسبق لأعمالها ومشترياتها التنسيق مع الهيئة للمواءمة في شأن متطلبات المحتوى المحلي.
TranslationWhen planning its works and procurement in advance, the government entity must coordinate with the Authority to align on local content requirements.
أ- آليات تفضيل المحتوى المحلي وكيفية احتسابه وتطبيقه في الأعمال والمشتريات، بما في ذلك نسبة الأفضلية في التقييم الفني والمالي للعروض أو نسبة الإلزامية للمحتوى المحلي من القيمة الإجمالية للعقد.
Translation(a) The mechanisms for preferring local content and how it is calculated and applied in works and procurement, including the preference percentage in the technical and financial evaluation of bids or the mandatory percentage of local content in the total value of the contract. [The first item the Preference Regulation must cover.]
خامسًا: استمرار العمل باللوائح المشار إليها في المادة (السادسة والتسعين) من نظام المنافسات والمشتريات الحكومية -الصادر بالمرسوم الملكي رقم (م/128) بتاريخ 1440/11/13هـ- والصادر في شأنها قرارا مجلس الوزراء رقم (245) بتاريخ 1441/3/29هـ، ورقم (537) بتاريخ 1441/8/21هـ.
TranslationFifth: the regulations referred to in article ninety-six of the Government Tenders and Procurement Law (issued by Royal Decree No. (M/128) dated 13/11/1440 AH), issued by Council of Ministers Decisions No. (245) dated 29/3/1441 AH and No. (537) dated 21/8/1441 AH, continue to apply.
2- قيام وزارة المالية وهيئة المحتوى المحلي والمشتريات الحكومية -كلٌّ فيما يخصه- بالتحقق من توافق اللوائح -المشار إليها في الفقرة (1) من هذا البند- مع أحكام النظام المشار إليه في البند (أولًا) من هذا القرار، والرفع عما يتطلب اتخاذ إجراء في شأنه.
Translation2. The Ministry of Finance and the Local Content and Government Procurement Authority (each within its remit) verify that the regulations (referred to in paragraph (1) of this item) are consistent with the provisions of the Law referred to in item (First) of this decision, and report on whatever requires action.
للهيئة -من تلقاء نفسها أو بناء على طلب من إحدى الجهات الحكومية- استخدام أسلوب التعاقد على توطين الصناعة ونقل المعرفة؛ وفقًا لقواعد مستقلة تصدرها الوزارة بالاشتراك مع الهيئة.
TranslationThe Authority may (on its own initiative or at the request of a government entity) use the method of contracting for industrial localisation and knowledge transfer, under separate rules the Ministry issues jointly with the Authority.
Etimad under the new law
The law calls it the Portal: a unified electronic portal for government procurement under the Ministry of Finance's supervision (art. 1). It does not use the name Etimad; the Ministry of Finance's FAQ on the 2019 law calls that law's portal the electronic portal, Etimad.
Procedures are put out through the Portal unless technical reasons or national security prevent it (art. 16). Public competition is announced on it (art. 29, para. 1), the tender documents are there in electronic form (art. 21, para. 2), and bids are submitted on it, encrypted (art. 36, para. 1).
The Ministry supervises the Portal and keeps developing it (art. 13, para. 1), and Decision 199 asks it to link the Portal technically with the Ministry of Justice, the Board of Grievances and other bodies, so that their decisions on the legal status of bidders and contractors reach it (item 11). The platform as it stands: Etimad.
عند حدوث عطل تقني في البوابة الإلكترونية (اعتماد)، يُمدد الإجراء المتعذر تنفيذه لمدة تماثل مدة التعطل.
TranslationWhen a technical failure occurs on the electronic portal (Etimad), the procedure that could not be carried out is extended by a period equal to the outage.
تطرح إجراءات المنافسات والمشتريات الحكومية من خلال البوابة -ما لم يتعذر ذلك لأسباب فنية أو لأسباب تتعلق بالأمن الوطني- وفقًا لما توضحه اللائحة.
TranslationGovernment tender and procurement procedures are put out through the Portal (unless that is impossible for technical reasons or reasons of national security), as the Regulation sets out.
يجب توفير نسخ إلكترونية لوثائق المنافسة في البوابة، وتحدد اللائحة الوسائل البديلة التي يجوز استخدامها إذا تعذر ذلك لأسباب فنية أو لأسباب تتعلق بالأمن الوطني.
TranslationElectronic copies of the tender documents must be made available on the Portal; the Regulation sets the alternative means that may be used if that is impossible for technical reasons or reasons of national security.
1- التنسيق مع وزارة العدل وديوان المظالم وغيرهما من الجهات ذات العلاقة، لإجراء عمليات الربط التقني بين البوابة الإلكترونية لنظام المنافسات والمشتريات الحكومية وتلك الجهات، لضمان تطبيق أحكام النظام والمواءمة بين تطبيق أحكامه وما يصدر عن تلك الجهات من قرارات تخص الوضع القانوني للمتنافسين والمتعاقدين مع الجهات الحكومية.
Translation1. Coordinating with the Ministry of Justice, the Board of Grievances and the other relevant bodies to link the electronic portal of the Government Tenders and Procurement Law technically with those bodies, to ensure the Law is applied and its application is aligned with the decisions those bodies issue on the legal status of bidders and of contractors with government entities. [The first task item 11 gives the Ministry of Finance.]
What carries over
Until the new law takes effect it is the 2019 law that applies, and tenders put out under it stay under it afterwards (item 3). Exceptions already granted continue (item 4), and so do the regulations issued under the 2019 law: the Preference Regulation and the regulations on conflicts of interest and on the conduct of those applying the law, Council of Ministers Decisions 245 and 537 (item 5).
Public competition remains the rule. The Ministry of Finance's FAQ on the 2019 law says so of that law, and article 28 of the new law says it again: all works and procurement are put out to public competition, except what the law exempts. And the procedures run through the Portal (art. 16), as they ran under the 2019 law through the portal the Ministry's FAQ calls Etimad.
الأصل هو أن تطرح جميع الأعمال والمشتريات في منافسة عامة، عدا ما يستثنى منها بموجب أحكام النظام ولائحته التنفيذية.
TranslationThe rule is that all works and procurement are put out to public competition, except what is exempted under the provisions of the Law and its Implementing Regulation.
تطرح جميع الأعمال والمشتريات في منافسة عامة عدا ما يستثنى منها وفقًا لأحكام النظام.
TranslationAll works and procurement are put out to public competition, except what is exempted under the provisions of the Law.
Frequently asked questions
01
When does Saudi Arabia's new procurement law take effect?
+
120 days after its publication in the Official Gazette (art. 101). Umm Al-Qura published it on 4 September 2026 (22/03/1448 AH). It then replaces the 2019 law, Royal Decree M/128 (art. 100), and tenders put out under the 2019 law stay under it (Royal Decree M/76, item 3).
02
What is the number of Saudi Arabia's new Government Tenders and Procurement Law?
+
Royal Decree M/76 of 27/02/1448 AH issued it, on Council of Ministers Decision 199 of 21/02/1448 AH. It replaces the law of Royal Decree M/128 of 13/11/1440 AH.
03
What is the direct purchase limit in Saudi Arabia under the new law?
+
An estimated cost of up to SAR 1,000,000, with priority to local small and medium enterprises (art. 32, para. 3). The Ministry of Finance gives the old ceiling as SAR 100,000. The entity must state and document its reasons (art. 32).
04
Does the new law apply to tenders already published on Etimad?
+
Works and procurement put out while the 2019 law was in force stay under the 2019 law. By way of exception, the Minister of Finance may apply some provisions of the new law to them under a mechanism he sets (Royal Decree M/76, item 3).
05
Are Saudi government tenders still on Etimad under the new law?
+
The law keeps the procedures on the Portal, a unified electronic portal under the Ministry of Finance (arts. 1 and 16): public competition is announced there and bids are submitted there, encrypted (arts. 29 and 36). The law does not name it; the Ministry of Finance's FAQ on the 2019 law calls that law's portal Etimad.
06
How much can a Saudi government contract change under the new law?
+
New items up to 10% of the contract or purchase order with the contractor's consent, existing items up 20% (consent for the increase beyond 10%) or down 20% (more with consent), and no more than 20% in total increase (art. 67).
07
Can a foreign company bid under the new Saudi procurement law?
+
The law provides for dealing with persons licensed outside the Kingdom: the entity makes sure that no more than one person licensed inside the Kingdom is qualified, and the Regulation sets the conditions (art. 3). Contracts are in Arabic (art. 52), guarantees come from a local bank or through one (art. 61), and payment is in riyals unless the Ministry agrees otherwise (art. 62).
08
What does the new Saudi law say about local content?
+
Priority goes to local small and medium enterprises, local content and listed companies, through the Preference Regulation (art. 9), which must set the preference percentage in evaluation or the mandatory share of local content (art. 98). Entities coordinate with the Local Content and Government Procurement Authority when planning (art. 12), and the current Preference Regulation stays in force (Royal Decree M/76, item 5).
TRINTA, "New Saudi Government Tenders and Procurement Law", Umm Al-Qura and the Ministry of Finance, edition 11 October 2026, https://trinta.ai/saudi-government-tenders-law-2027 (accessed [date]).
This page says what the official texts say; it is not legal advice. Many details are left to the Implementing Regulation (art. 99), and each procedure's own documents govern it.